๐Ÿ“Review Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Lakeshore Drive and Harvest Hill Road Improvements

Intersection of Lakeshore Dr. and Harvest Hill Rd., Cleburne, TX, 76033
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2025017508
$600K
Project Value
52,200
Square Feet
$11/sqft
Cost/SqFt
2 years
Duration
Registered:Apr 25, 2025
Start:Jun 30, 2025
Target:Jun 30, 2027
Remaining:567 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

The project will reconstruction lakeshore Drive, Harvest Hill Road and Boat ramp access road with a concrete curb and gutter section. The new corridor will have new sidewalks, parking spaces and ADA ramps.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
April 25, 2025
Review Complete
April 25, 2025
Construction Start
June 30, 2025
Expected Completion
June 30, 2027

๐Ÿ—บ๏ธProject Location

Loading map...

Quick Actions

TDLR ID: TABS2025017508

Property Owner

Design Firm

Registered Accessibility Specialist

๐Ÿ“‹
ROSS A,THOMAS
RAS #1241
1407 W UNIVERSITY DR, MCKINNEY, TX 75069