๐Review Complete๐ง Renovation/Alteration๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Lakeshore Drive and Harvest Hill Road Improvements
Intersection of Lakeshore Dr. and Harvest Hill Rd., Cleburne, TX, 76033
Construction50%
๐Project Metrics
TDLR #TABS2025017508$600K
Project Value
52,200
Square Feet
$11/sqft
Cost/SqFt
2 years
Duration
Registered:Apr 25, 2025
Start:Jun 30, 2025
Target:Jun 30, 2027
Remaining:567 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
The project will reconstruction lakeshore Drive, Harvest Hill Road and Boat ramp access road with a concrete curb and gutter section. The new corridor will have new sidewalks, parking spaces and ADA ramps.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
April 25, 2025
Review Complete
April 25, 2025
Construction Start
June 30, 2025
Expected Completion
June 30, 2027
๐Related Projects
Property Owner
๐ค
City of Cleburne
Contact: Laura Melton
2 projects ยท $2.7M
10 N. Robinson St.,, Cleburne, Texas 76031
Design Firm
๐๏ธ
Kimley-Horn and Associates, Inc.
6 projects ยท $13.7M
801 Cherry St. Ste 1300,, Fort Worth, Texas 76102