Inspection Complete๐ง Renovation/Alteration๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Stallings Boulevard Garage Exit Modifications
500 Gene Stallings BI, College Station, TX, 77843
Final Inspection85%
๐Project Metrics
TDLR #TABS2025017549$850K
Project Value
78,000
Square Feet
$11/sqft
Cost/SqFt
3 months
Duration
Registered:Apr 25, 2025
Start:May 12, 2025
Target:Aug 15, 2025
โ
Inspection Complete
Final inspection completed, awaiting project closure
๐Scope of Work
Structural, electrical and technology modifications to the parking garage. New pedestrian entrance/exit. Pedestrian path modifications exterior of the garage.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
April 25, 2025
Inspection Complete
April 25, 2025
Construction Start
May 12, 2025
Expected Completion
August 15, 2025
Property Owner
๐ค
Texas A&M University Transportation Services
Contact: Randy Harrison
5 projects ยท $10.1M
1250 TAMU, College Station, Texas 77843
Design Firm
๐๏ธ
Kimley-Horn and Associates, Inc.
6 projects ยท $13.7M
614 Holleman Dr. E Suite 1100, College Station, Texas 77840