📝Review Complete🏗️ New Construction💵 This project is privately funded, on private land for private use.
New Metal Building
5602 FM 2403, Alvin, TX, 77511
Construction50%
📊Project Metrics
TDLR #TABS2025017675$600K
Project Value
4,800
Square Feet
$125/sqft
Cost/SqFt
8 months
Duration
Registered:Apr 28, 2025
Start:Jul 1, 2025
Target:Mar 1, 2026
Remaining:81 days
📝
Review Complete
Design review complete, construction may proceed
📋Scope of Work
New metal bldg; 2x2400
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
April 28, 2025
Review Complete
April 28, 2025
Construction Start
July 1, 2025
Expected Completion
March 1, 2026