๐Review Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Liberty Hill Bypass Improvements
Liberty Hill, Liberty, TX 78642, TX, 78642
๐Project Overview
$14.1M
Est. Cost
1
Square Feet
1y 11mo
Duration
31
Days Left
๐Scope of Work
Construction of new roadway consisting of grading, base, paving, bridge structures, drainage, structures, ditches, water quality BMPs, signing, and pavement markings
๐ Project Timeline
Registered
May 5, 2025
Review Complete
May 5, 2025
Construction Start
February 15, 2024
Expected Completion
December 31, 2025
๐บ๏ธLocation
Property Owner
๐ค
Williamson County
Contact: Bob Daigh
6 total projects
3151 S.E. Inner Loop, Suite B, Georgetown, Texas 78626
512 943 3330
Design Firm
๐๏ธ
LJA Engineering, Inc.
6 total projects
2700 La Frontera, Suite 200, Roundrock, Texas 78681
512-439-4774
Registered Specialist
๐
JESUS E,LARDIZABAL
RAS #1051
3616 FAR WEST BLVD # 117288, AUSTIN, TX 78731
(512) 410-7059