๐Ÿ“Review Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Alps Dr, Concepcion St and Hollings St (CSJ: 0924-06-655, etc.)

Various Locations, El Paso, TX, 79904
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2025018439
$616K
Project Value
1,452
Square Feet
$424/sqft
Cost/SqFt
6 months
Duration
Registered:May 7, 2025
Start:Sep 1, 2025
Target:Mar 1, 2026
Remaining:81 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Replace bridge, bridge class culverts and approaches.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
May 7, 2025
Review Complete
May 7, 2025
Construction Start
September 1, 2025
Expected Completion
March 1, 2026

๐Ÿ—บ๏ธProject Location

Loading map...

Quick Actions

TDLR ID: TABS2025018439

Design Firm

๐Ÿ›๏ธ
TxDOT District: El Paso
13301 Gateway Blvd, El Paso, Texas 79928

Registered Accessibility Specialist

๐Ÿ“‹
FRANK,FONSECA
RAS #1184
526 WILLIAMSBURG PL, SAN ANTONIO, TX 78201