Shaver Phase II Allendale Road to Vince Bayou Bridge
Shaver Street, Allendale Road to Vince Bayou Brid, Pasadena, TX, 77506
Construction50%
๐Project Metrics
TDLR #TABS2025018939$10.5M
Project Value
272,000
Square Feet
$39/sqft
Cost/SqFt
1y 6mo
Duration
Registered:May 14, 2025
Start:Sep 1, 2025
Target:Feb 23, 2027
Remaining:440 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Reconstruction of Shaver Street from Allendale Road to the Vince Bayou Bridge of 10" concrete pavement, storm sewer, water line replacement, sanitary sewer, ADA compliant sidewalk, driveway replacements, and trees.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
May 14, 2025
Review Complete
May 14, 2025
Construction Start
September 1, 2025
Expected Completion
February 23, 2027
๐Related Projects
Property Owner
๐ค
City of Pasadena
Contact: Y Nhi Tran
6 projects ยท $28.5M
1149 Ellsworth Drive, Pasadena, TX 77506, Pasadena, Texas 77506
Design Firm
๐๏ธ
BinkleyBarfield | DCCM
3 projects ยท $23.6M
1710 Seamist Drive, Houston, Texas 77008