๐Review Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
US 77 (CSJ: 0327-09-002)
Fr.: N of SH 285 To: Kleberg/Kenedy County Line, Riviera, TX, 78379
Construction50%
๐Project Metrics
TDLR #TABS2025018976$207.7M
Project Value
2,646
Square Feet
$78514/sqft
Cost/SqFt
6y 1mo
Duration
Registered:May 14, 2025
Start:Oct 2, 2025
Target:Oct 10, 2031
Remaining:2130 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Construction of a four lane divided freeway relief route on new location around Riviera, Texas.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
May 14, 2025
Review Complete
May 14, 2025
Construction Start
October 2, 2025
Expected Completion
October 10, 2031
Property Owner
๐ค
TxDOT District: Corpus Christi
Contact: Malcolm Gonzalez, P.E.
5 projects ยท $263.7M
1701 S. Padre Island Drive, Corpus Christi, Texas 78416