๐Review Complete๐ง Additions to Existing Building๐ต This project is privately funded, on private land for private use.
Addition to Atlanta Methodist Church
701 Lindsay Lane, Atlanta, TX, 75551
Construction50%
๐Project Metrics
TDLR #TABS2025019289$3.5M
Project Value
14,000
Square Feet
$250/sqft
Cost/SqFt
11 months
Duration
Registered:May 19, 2025
Start:May 26, 2025
Target:May 1, 2026
Remaining:142 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Alterations to a portion of the existing building and addition of a new sanctuary.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
May 19, 2025
Review Complete
May 19, 2025
Construction Start
May 26, 2025
Expected Completion
May 1, 2026