Bus Maintenance Facility

627 E US Highway 67, Rankin, TX, 79778
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2025020119
$6.6M
Project Value
29,667
Square Feet
$222/sqft
Cost/SqFt
1 year
Duration
Registered:May 30, 2025
Start:Jul 1, 2025
Target:Jun 30, 2026
Remaining:202 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Construction of a Bus Maintenance Facility will be approx. 19,000 SF for Base Bid and approx. 10,667 SF more to add 5 bays to the facility. The maintenance facility will be a Pre-Engineered Metal Building and will house some offices.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
May 30, 2025
Review Complete
May 30, 2025
Construction Start
July 1, 2025
Expected Completion
June 30, 2026

๐Ÿ—บ๏ธProject Location

Loading map...

Quick Actions

TDLR ID: TABS2025020119

Registered Accessibility Specialist

๐Ÿ“‹
STEPHEN D,MACPHIE
RAS #307
4210 E MUNICIPAL DRIVE APT 6, LUBBOCK, TX 79403