📊Project Overview

$2.2M
Est. Cost
703
Square Feet
3 months
Duration
32
Days Left

📋Scope of Work

Project consists of relocating existing Cap Metro Rail Equipment across the street on 4th Street. Scope of work includes selective demolition, site utilities, a new concrete equipment pad, and site landscaping. Total new square footage is 703.

📅Project Timeline

Registered
May 30, 2025
Review Complete
May 30, 2025
Construction Start
September 25, 2025
Expected Completion
January 1, 2026

🗺️Location

📄Related Austin Permits

City permits found at this location

403 1/2 TRINITY ST
Same location

Adding power to a bus stop for CMTA at (Brush Square NB) 403.5 Trinity St.

FinalElectrical PermitUpgradeJan 2025
Details
2024-164008 EP
🔧J.S. Electric, Inc.
405 1/2 E 4TH ST
Same location

Remove wiring to vending machine validating machine rail road control enclosure four pole lights one canopy light and install one each new lighting contactor time clock and photo cell for lighting only.

FinalElectrical PermitRemodelFeb 2009
Details
2009-011082 EP
🔧Richard's Electric L.P.
405 1/2 E 4TH ST
Same location

Install elect service for capital metro light rail only.

FinalElectrical PermitRemodelSep 2008
Details
2008-070967 EP
🔧Ellhouse Industries
408 1/2 E 4TH ST
136 ft away

Temp meter loop for construction trailer only Ref# SP-2018-0163C

ExpiredElectrical PermitRepairMay 2019
Details
2019-072248 EP
🔧Alpha and Omega Industries, LLC DBA Diversified Elelctrical Solutions

Property Owner

👤
City of Austin CDS
Contact: Riley Triggs
P.O. Box 1088, Austin, Texas 78767
512.636.3521

Design Firm

🏛️
LMN/Page Joint Venture
200 W. 6th Street, Suite 1800, Austin, Texas 78701
512.382.3496

Registered Specialist

📋
ELAINE K,ANDERSEN
RAS #1284
PO BOX 143214, AUSTIN, TX 78714
(512) 415-6000

Official Record

View on TDLR
ID: TABS2025020186