📝Review Complete🏗️ New Construction💵 This project is privately funded, on private land for private use.
New Office
11110 Hwy 191, Midland, TX, 79707
Construction50%
📊Project Metrics
TDLR #TABS2025020320$1.2M
Project Value
12,000
Square Feet
$100/sqft
Cost/SqFt
6 months
Duration
Registered:Jun 2, 2025
Start:Jun 9, 2025
Target:Dec 14, 2025
Remaining:4 days
📝
Review Complete
Design review complete, construction may proceed
📋Scope of Work
New Office Construction
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
June 2, 2025
Review Complete
June 2, 2025
Construction Start
June 9, 2025
Expected Completion
December 14, 2025