📋Project Registered🏗️ New Construction💵 This project involves public funds, public land, or is a Federally funded roadway project.
Stenger St. Hike and Bike
Stenger from Bus77 to FaninSt., San Benito, TX, 78586
Pre-Construction15%
📊Project Metrics
TDLR #TABS2025020690$2.4M
Project Value
50,380
Square Feet
$47/sqft
Cost/SqFt
7 months
Duration
Registered:Jun 6, 2025
Start:Dec 15, 2025
Target:Jul 24, 2026
Remaining:226 days
📋
Project Registered
Project has been registered with TDLR and is in pre-construction phase
📋Scope of Work
Construct a shared use path and sidewalk.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
June 6, 2025
Construction Start
December 15, 2025
Expected Completion
July 24, 2026