๐Review Complete๐ง Additions to Existing Building๐ต This project is privately funded, on private land for private use.
JBS CACTUS FABRICATION FLOOR EXPANSION
5950 TRAILS END RD, Cactus, TX, 79013
Construction50%
๐Project Metrics
TDLR #TABS2025020724$58.7M
Project Value
152,548
Square Feet
$385/sqft
Cost/SqFt
1y 1mo
Duration
Registered:Jun 6, 2025
Start:Aug 19, 2025
Target:Sep 24, 2026
Remaining:288 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
123,530 SF 2-STORY ADDITION AND 28,018 SF RENOVATION OF TYPE II-B CONSTRUCTION AND F-1 OCCUPANCY FOR THE REPLACEMENT AND EXPANSION OF THE FABRICATION FLOOR
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
June 6, 2025
Review Complete
June 6, 2025
Construction Start
August 19, 2025
Expected Completion
September 24, 2026