๐Review Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
White Avenue Sidewalk and Accessibility Improvements
White Avenue (from Redbud Blvd to Tennesee St), Mckinney, TX, 75069
Construction50%
๐Project Metrics
TDLR #TABS2025021132$1.3M
Project Value
6,000
Square Feet
$210/sqft
Cost/SqFt
6 months
Duration
Registered:Jun 12, 2025
Start:Oct 16, 2025
Target:Apr 3, 2026
Remaining:114 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Installing 6' sidewalk and ramps along north side of White Avenue(6,000 ft corridor, narrowing street ~3' off the north curb line.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
June 12, 2025
Review Complete
June 12, 2025
Construction Start
October 16, 2025
Expected Completion
April 3, 2026
Property Owner
๐ค
City of McKinney
Contact: Alvin Maliakal
6 projects ยท $148.4M
401 E. Virginia Street, McKinney, Texas 75069
Design Firm
๐๏ธ
Lockwood, Andrews & Newnam, Inc.
5 projects ยท $80.9M
2801 Network Blvd, Suite 100, Frisco, Texas 75034