๐Review Complete๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
LA Terminal
5602 BOB Bullock Loop, Laredo, TX, 78041
Construction50%
๐Project Metrics
TDLR #TABS2025021183$4.1M
Project Value
52,560
Square Feet
$77/sqft
Cost/SqFt
8 months
Duration
Registered:Jun 12, 2025
Start:Jun 19, 2025
Target:Feb 25, 2026
Remaining:65 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Flex Building
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
June 12, 2025
Review Complete
June 12, 2025
Construction Start
June 19, 2025
Expected Completion
February 25, 2026
๐Related Projects
Property Owner
๐ค
LA Terminal
Contact: Diego E. Benavides Chavez.
5602 Bob Bullock Loop, Laredo, Texas 78043