๐Ÿ“‹Project Registered๐Ÿ”ง Additions to Existing Building๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Clemons Creek Middle School Classroom Addition

2700 Leonard Ave, Anna, TX, 75409
Pre-Construction15%

๐Ÿ“ŠProject Metrics

TDLR #TABS2025021529
$7.0M
Project Value
13,065
Square Feet
$536/sqft
Cost/SqFt
10 months
Duration
Registered:Jun 18, 2025
Start:Jul 20, 2025
Target:May 20, 2026
Remaining:161 days
๐Ÿ“‹

Project Registered

Project has been registered with TDLR and is in pre-construction phase

๐Ÿ“‹Scope of Work

2-story 12 Classroom addition (13,065 SF) with site work around the addition. A new visitor bleacher addition to the existing track and field with additional site renovations.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
June 18, 2025
Construction Start
July 20, 2025
Expected Completion
May 20, 2026

๐Ÿ—บ๏ธProject Location

Loading map...

Quick Actions

TDLR ID: TABS2025021529

Design Firm

๐Ÿ›๏ธ
WRA Architects
6 projects ยท $68.8M
6000 Headquarters Dr suite 600, Plano, Texas 75024

Registered Accessibility Specialist

๐Ÿ“‹
RONALD L,DAVIS
RAS #83
3001 MOTLEY DR STE J, MESQUITE, TX 75150