📋Project Registered🏗️ New Construction💵 This project is privately funded, on private land for private use.
PTAA
3200 S. FM 528, Royse City, TX, 75189
Pre-Construction15%
📊Project Metrics
TDLR #TABS2025022691$4.0M
Project Value
42,000
Square Feet
$95/sqft
Cost/SqFt
1 year
Duration
Registered:Jul 3, 2025
Start:Aug 15, 2025
Target:Aug 21, 2026
Remaining:254 days
📋
Project Registered
Project has been registered with TDLR and is in pre-construction phase
📋Scope of Work
Construct new Classroom/Gym building
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
July 3, 2025
Construction Start
August 15, 2025
Expected Completion
August 21, 2026