๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

DSV Breakroom and Office Expansion

3701 Midpoint Drive, Lancaster, TX, 75134
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2025022707
$961K
Project Value
3,700
Square Feet
$260/sqft
Cost/SqFt
5 months
Duration
Registered:Jul 3, 2025
Start:Aug 11, 2025
Target:Dec 31, 2025
Remaining:21 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

The addition of a central breakroom and office.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
July 3, 2025
Review Complete
July 3, 2025
Construction Start
August 11, 2025
Expected Completion
December 31, 2025

๐Ÿ—บ๏ธProject Location

Loading map...

Quick Actions

TDLR ID: TABS2025022707

Property Owner

๐Ÿ‘ค
Sterling Investments
Contact: Kelsey Kupish
712 5th Ave., Suite 11A, New York, New York 10019

Design Firm

Registered Accessibility Specialist

๐Ÿ“‹
CONNIE,FLEMING
RAS #140
161 MEADOW POND CT, BRIDGEPORT, TX 76426