๐Ÿ“Review Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project is privately funded, on private land for private use.

Galveston Urban Ministries Kitchen Buildout

1804 69TH STREET, Galveston, TX, 77551
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2025023100
$100K
Project Value
1,500
Square Feet
$67/sqft
Cost/SqFt
4 months
Duration
Registered:Jul 9, 2025
Start:Sep 1, 2025
Target:Dec 31, 2025
Remaining:21 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Kitchen buildout within an existing building.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
July 9, 2025
Review Complete
July 9, 2025
Construction Start
September 1, 2025
Expected Completion
December 31, 2025

๐Ÿ—บ๏ธProject Location

Loading map...

Quick Actions

TDLR ID: TABS2025023100

Property Owner

Design Firm

๐Ÿ›๏ธ
Mark W. Todd Architects
6 projects ยท $24.8M
1440 Lake Front Circle Suite 120, The Woodlands, Texas 77380

Registered Accessibility Specialist

๐Ÿ“‹
TIM,MULLINS
RAS #167
1130 MAIN SAIL LOOP, WILLIS, TX 77318