Joshua HS CTE Addition and Renovation
909 S Broadway St, Joshua, TX, 76058
Pre-Construction15%
๐Project Metrics
TDLR #TABS2025023248$25.0M
Project Value
56,000
Square Feet
$446/sqft
Cost/SqFt
1y 5mo
Duration
Registered:Jul 11, 2025
Start:Aug 1, 2025
Target:Dec 26, 2026
Remaining:381 days
๐
Project Registered
Project has been registered with TDLR and is in pre-construction phase
๐Scope of Work
Project consists of renovations to the existing CTE building and a 2 story storm shelter addition. Existing renovation area is 25,000 SF and the 2 story addition is 31,000 SF.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
July 11, 2025
Construction Start
August 1, 2025
Expected Completion
December 26, 2026
๐Related Projects
๐คBy Owner
$93.0M total๐๏ธBy Design Firm
$33.0M totalProperty Owner
๐ค
Joshua ISD
Contact: Corey Hickerson
4 projects ยท $93.0M
310 E 18th Street, Joshua, Texas 76058
Design Firm
๐๏ธ
WRA Architects Inc.
2 projects ยท $33.0M
6000 Headquarters DR #600, Plano, Texas 75024