✅Inspection Complete🔧 Renovation/Alteration💵 This project involves public funds, public land, or is a Federally funded roadway project.
TIRZ 9 - Sidewalk, Curbs, Curb Ramps and Restriping Project Along West Orem Dr. (Hiram Clarke to Bu
W Orem Dr Between Hiram Clarke & Buffalo Speedway, Houston, TX, 77045
Final Inspection85%
📊Project Metrics
TDLR #TABS2025023347$933K
Project Value
1
Square Feet
$932823/sqft
Cost/SqFt
9 months
Duration
Registered:Jul 11, 2025
Start:Nov 1, 2024
Target:Jul 20, 2025
✅
Inspection Complete
Final inspection completed, awaiting project closure
📋Scope of Work
Sidewalk removal and replacement, ADA ramps removal and replacement, driveway removal and replacement at various locations, roadway restriping, poetry concrete stamping at landings.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
July 11, 2025
Inspection Complete
July 11, 2025
Construction Start
November 1, 2024
Expected Completion
July 20, 2025