📝Review Complete🔧 Additions to Existing Building💵 This project is privately funded, on private land for private use.
Saylee Greer Office Expansion
4187 Stahl Road, San Antonio, TX, 78217
Construction50%
📊Project Metrics
TDLR #TABS2025023400$550K
Project Value
1,903
Square Feet
$289/sqft
Cost/SqFt
7 months
Duration
Registered:Jul 14, 2025
Start:Aug 1, 2025
Target:Mar 1, 2026
Remaining:81 days
📝
Review Complete
Design review complete, construction may proceed
📋Scope of Work
1903 square foot addition to existing landscape architecture office and siding replacement of existing structure
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
July 14, 2025
Review Complete
July 14, 2025
Construction Start
August 1, 2025
Expected Completion
March 1, 2026