Mabank Junior High Additions & Renovations
822 W Mason St Mabank, TX 75147, Mabank, TX, 75147
Construction50%
๐Project Metrics
TDLR #TABS2025023759$14.3M
Project Value
28,225
Square Feet
$508/sqft
Cost/SqFt
1y 3mo
Duration
Registered:Jul 17, 2025
Start:Sep 15, 2025
Target:Dec 21, 2026
Remaining:376 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
A new classroom addition (storm shelter), a new restroom addition to serve the existing cafeteria, kitchen and cafeteria renovation, courtyard renovations, restroom fixtures replacement, miscellaneous demolition.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
July 17, 2025
Review Complete
July 17, 2025
Construction Start
September 15, 2025
Expected Completion
December 21, 2026
Property Owner
๐ค
Mabank ISD
Contact: Scott Hyde
5 projects ยท $97.0M
310 E Market St., Mabank, Texas 75147
Design Firm
๐๏ธ
Claycomb Associates Architects
6 projects ยท $66.5M
6600 LYNDON B JOHNSON FWY SUITE 200, DALLAS, Texas 75240