📝Review Complete🏗️ New Construction💵 This project is privately funded, on private land for private use.
Enlake Pass
1630 Northlake Pass, Universal City, TX, 78148
Construction50%
📊Project Metrics
TDLR #TABS2025024055$2.4M
Project Value
19,200
Square Feet
$125/sqft
Cost/SqFt
5 months
Duration
Registered:Jul 22, 2025
Start:Aug 15, 2025
Target:Jan 22, 2026
Remaining:43 days
📝
Review Complete
Design review complete, construction may proceed
📋Scope of Work
Shell Building warehouse with office space
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
July 22, 2025
Review Complete
July 22, 2025
Construction Start
August 15, 2025
Expected Completion
January 22, 2026
Property Owner
👤
MDB407 LLC
Contact: Rocio G Bartolucci
12150 NE 19th Ave #8, North Miami, Florida 33181