๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Adler Road Phase 1

Adler Road at Plant, Boerne, TX, 78006
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2025024256
$4.8M
Project Value
7,875
Square Feet
$604/sqft
Cost/SqFt
10 months
Duration
Registered:Jul 24, 2025
Start:Aug 1, 2025
Target:Jun 4, 2026
Remaining:176 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Construct new culverts at two low water crossings

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
July 24, 2025
Review Complete
July 24, 2025
Construction Start
August 1, 2025
Expected Completion
June 4, 2026

๐Ÿ—บ๏ธProject Location

Loading map...

Quick Actions

TDLR ID: TABS2025024256

Design Firm

๐Ÿ›๏ธ
Freese and Nichols, Inc.
6 projects ยท $27.6M
9601 McAllister Freeway Suite 1008, San Antonio, Texas 78216

Registered Accessibility Specialist

๐Ÿ“‹
FRANK,FONSECA
RAS #1184
526 WILLIAMSBURG PL, SAN ANTONIO, TX 78201