📝Review Complete🏗️ New Construction💵 This project is privately funded, on private land for private use.
Salemi's Storage
4001 7th Street, Bay City, TX, 77414
Construction50%
📊Project Metrics
TDLR #TABS2025024352$690K
Project Value
35,100
Square Feet
$20/sqft
Cost/SqFt
4 months
Duration
Registered:Jul 25, 2025
Start:Dec 29, 2025
Target:Apr 13, 2026
Remaining:124 days
📝
Review Complete
Design review complete, construction may proceed
📋Scope of Work
Three (3) Climatized 11,700 Storage Buildings. Structural Steel Framing / Metal
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
July 25, 2025
Review Complete
July 25, 2025
Construction Start
December 29, 2025
Expected Completion
April 13, 2026