๐Review Complete๐ง Renovation/Alteration๐ต This project is privately funded, on private land for private use.
Central Bank - West Houston
11201 Clay Rd, Houston, TX, 77041
Construction50%
๐Project Metrics
TDLR #TABS2025024529$13.1M
Project Value
35,872
Square Feet
$365/sqft
Cost/SqFt
1y 8mo
Duration
Registered:Jul 28, 2025
Start:Oct 15, 2025
Target:Jun 15, 2027
Remaining:552 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Renovation of existing and addition to existing bank headquarters building.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
July 28, 2025
Review Complete
July 28, 2025
Construction Start
October 15, 2025
Expected Completion
June 15, 2027