Krum ISD | Phoenix House | 01902-08-01
4205 FM 2450, Krum, TX, 76249
Completed100%
๐Project Metrics
TDLR #TABS2025024589$3.0M
Project Value
3,795
Square Feet
$791/sqft
Cost/SqFt
4 months
Duration
Registered:Jul 29, 2025
Start:Sep 12, 2025
Target:Jan 10, 2026
Remaining:31 days
๐
Project Closed
Project has been completed and closed
๐Scope of Work
renovation
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
July 29, 2025
Project Closed
July 29, 2025
Construction Start
September 12, 2025
Expected Completion
January 10, 2026