๐Review Complete๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
Christus Tyler Parking Lot Improvements
800 South Beckham Ave., Tyler, TX, 75701
Construction50%
๐Project Metrics
TDLR #TABS2025024696$1.2M
Project Value
139,574
Square Feet
$9/sqft
Cost/SqFt
3 months
Duration
Registered:Jul 30, 2025
Start:Sep 1, 2025
Target:Dec 1, 2025
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Construction of new paving for additional parking and re-stripe a portion of existing parking lot. 139,574 SF
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
July 30, 2025
Review Complete
July 30, 2025
Construction Start
September 1, 2025
Expected Completion
December 1, 2025