School of Rock Kyle
5581 Kyle Center Dr Ste 204, Kyle, TX, 78640
📊Project Overview
$500K
Est. Cost
2,800
Square Feet
4 months
Duration
46
Days Left
📋Scope of Work
TENANT IMPROVEMENT CONSISTING OF THE CONSTRUCTION OF A NEW SKILL DEVELOPMENT FACILITY WITHIN AN EXISTING BUILDING SHELL, TO INCLUDE ALL ELECTRICAL, PLUMBING AND MECHANICAL MODIFICATIONS, INTERIOR PARTITIONS AND EQUIPMENT. NO STRUCTURAL OR STOREFRONT
📅Project Timeline
Registered
August 7, 2025
Review Complete
August 7, 2025
Construction Start
September 15, 2025
Expected Completion
January 15, 2026
🗺️Location
Property Owner
👤
Tony Jacob
Contact: Katy Bowler
2110 W. Slaughter Lane Ste 107-106, Austin, Texas 78748
(512) 971-2406
Design Firm
Registered Specialist
📋
CLINTON P,RYAN
RAS #1333
3919 ROSSER SQ, DALLAS, TX 75244
(972) 822-0554
Tenant
🏢
Paige Gorman
(210) 606-6867