๐Review Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
PRAIRIELAND BCP 10 & SOUTH HALF LAKE AMENITY
BRIDGELAND CREEK PARKWAY & MIGRATION WAY, Cypress, TX, 77433
Construction50%
๐Project Metrics
TDLR #TABS2025025483$1.3M
Project Value
360,000
Square Feet
$4/sqft
Cost/SqFt
9 months
Duration
Registered:Aug 8, 2025
Start:Dec 1, 2025
Target:Sep 1, 2026
Remaining:265 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Concrete Trail, Planting, Irrigation, Decorative Stone Flume
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
August 8, 2025
Review Complete
August 8, 2025
Construction Start
December 1, 2025
Expected Completion
September 1, 2026
๐Related Projects
๐คBy Owner
$1.9M totalProperty Owner
๐ค
Howard Hughes Corp
Contact: Austin Sherrill
3 projects ยท $1.9M
23720 HOUSE HAHL RD., CYPRESS, TX, Texas 77433