๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

25017 - Cargo Center 2 TI

2520 Airfield Drive #100, Dfw Airport, TX, 75261
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2025026764
$100K
Project Value
3,744
Square Feet
$27/sqft
Cost/SqFt
4 months
Duration
Registered:Aug 26, 2025
Start:Oct 1, 2025
Target:Feb 1, 2026
Remaining:53 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

The project consists of modifications to the existing elevator and equipment inside the existing Cargo Center 3 shell building at DFW Airport.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
August 26, 2025
Review Complete
August 26, 2025
Construction Start
October 1, 2025
Expected Completion
February 1, 2026

๐Ÿ—บ๏ธProject Location

Loading map...

Quick Actions

TDLR ID: TABS2025026764

Property Owner

Design Firm

Registered Accessibility Specialist

๐Ÿ“‹
CLINTON L,COULTAS
RAS #1573
3905 TITAN TRL, DENTON, TX 76209