๐Review Complete๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
Andy's Frozen Custard - Broadway
8338 Broadway, San Antonio, TX, 78209
Construction50%
๐Project Metrics
TDLR #TABS2025026779$1.9M
Project Value
1,757
Square Feet
$1081/sqft
Cost/SqFt
5 months
Duration
Registered:Aug 26, 2025
Start:Oct 1, 2025
Target:Feb 28, 2026
Remaining:80 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
New 1757 SF drive-thru frozen custard retail store building, new civil, landscaping, and MEP building systems included.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
August 26, 2025
Review Complete
August 26, 2025
Construction Start
October 1, 2025
Expected Completion
February 28, 2026
๐Related Projects
๐คBy Owner
$3.8M totalProperty Owner
๐ค
Suelo Dulce Cibolo, LLC
Contact: Joseph Shields
2 projects ยท $3.8M
755 E. Mulberry Avenue Suite 600, San Antonio, Texas 78212
Design Firm
๐๏ธ
KNRG Architects
6 projects ยท $11.9M
13438 Bandera Rd. Suite 202, Helotes, Texas 78023