๐Review Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Bob Hope Middle School
304 N. Pruett St., Baytown, TX, 77520
Construction50%
๐Project Metrics
TDLR #TABS2025027021$6.0M
Project Value
24,133
Square Feet
$249/sqft
Cost/SqFt
4 months
Duration
Registered:Aug 29, 2025
Start:Oct 1, 2025
Target:Feb 1, 2026
Remaining:53 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
The project consists of a new 24,133 sq ft.classroom building.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
August 29, 2025
Review Complete
August 29, 2025
Construction Start
October 1, 2025
Expected Completion
February 1, 2026
Property Owner
Design Firm
๐๏ธ
Sigma Engineers, Inc.
6 projects ยท $10.9M
4099 Calder Ave., Beaumont, Texas 77706