📝Review Complete🔧 Renovation/Alteration💵 This project is privately funded, on private land for private use.
1302 S 53rd Street Remodel
1302 S 53rd St, Temple, TX, 76504
Construction50%
📊Project Metrics
TDLR #TABS2026000436$200K
Project Value
5,000
Square Feet
$40/sqft
Cost/SqFt
5 months
Duration
Registered:Sep 6, 2025
Start:Oct 1, 2025
Target:Feb 15, 2026
Remaining:67 days
📝
Review Complete
Design review complete, construction may proceed
📋Scope of Work
Remodel of Existing Building
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
September 6, 2025
Review Complete
September 6, 2025
Construction Start
October 1, 2025
Expected Completion
February 15, 2026