๐Ÿ“Review Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project is privately funded, on private land for private use.

Administrative Restack- Phase 5A- Phase 1 Package

7007 Bertner Ave., Houston, TX, 77030
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2026000460
$126K
Project Value
600
Square Feet
$210/sqft
Cost/SqFt
2 months
Duration
Registered:Sep 8, 2025
Start:Sep 15, 2025
Target:Nov 17, 2025
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Replacing and/or providing door hardware where needed within scope of work on floors 2, 11 and 17

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
September 8, 2025
Review Complete
September 8, 2025
Construction Start
September 15, 2025
Expected Completion
November 17, 2025

๐Ÿ—บ๏ธProject Location

Loading map...

Quick Actions

TDLR ID: TABS2026000460

Design Firm

๐Ÿ›๏ธ
THIEL Design Group
6 projects ยท $4.5M
611 W. 22nd Street, Ste 202, Houston, Texas 77008

Registered Accessibility Specialist

๐Ÿ“‹
JANEL CARONA,BLOOM
RAS #120
11555 BEAMER RD STEE 500, HOUSTON, TX 77089