๐Review Complete๐ง Renovation/Alteration๐ต This project is privately funded, on private land for private use.
MHHS Cypress Campus Expansion - Cath Lab
27800 Northwest Freeway, Cypress, TX, 77433
Construction50%
๐Project Metrics
TDLR #TABS2026000774$1.7M
Project Value
1,750
Square Feet
$971/sqft
Cost/SqFt
1y 7mo
Duration
Registered:Sep 12, 2025
Start:Oct 20, 2025
Target:May 1, 2027
Remaining:507 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Addition/renovation to the level 2 Cath/IR Lab. Scope of work is 1,750SF
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
September 12, 2025
Review Complete
September 12, 2025
Construction Start
October 20, 2025
Expected Completion
May 1, 2027