๐Review Complete๐ง Renovation/Alteration๐ต This project is privately funded, on private land for private use.
Eldorado Dental
2148 N. Lake Forest Dr, Ste 300, Mckinney, TX, 75074
Construction50%
๐Project Metrics
TDLR #TABS2026000905$365K
Project Value
2,000
Square Feet
$183/sqft
Cost/SqFt
4 months
Duration
Registered:Sep 15, 2025
Start:Oct 27, 2025
Target:Feb 20, 2026
Remaining:72 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Interior finish out of shell space.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
September 15, 2025
Review Complete
September 15, 2025
Construction Start
October 27, 2025
Expected Completion
February 20, 2026