📝Review Complete🔧 Renovation/Alteration💵 This project is privately funded, on private land for private use.
Animal Treatment Center
9294 McCombs St., El Paso, TX, 79924
Construction50%
📊Project Metrics
TDLR #TABS2026001441$150K
Project Value
2,831
Square Feet
$53/sqft
Cost/SqFt
6 months
Duration
Registered:Sep 22, 2025
Start:Sep 1, 2025
Target:Feb 26, 2026
Remaining:78 days
📝
Review Complete
Design review complete, construction may proceed
📋Scope of Work
Tenant Improvement
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
September 22, 2025
Review Complete
September 22, 2025
Construction Start
September 1, 2025
Expected Completion
February 26, 2026