๐Review Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Central ISD New Maintenance Facility
SEQ of North Highway 69 and Thigpen Road, Pollok, TX, 75969
Construction50%
๐Project Metrics
TDLR #TABS2026002594$1.3M
Project Value
8,500
Square Feet
$153/sqft
Cost/SqFt
9 months
Duration
Registered:Oct 6, 2025
Start:Nov 18, 2025
Target:Aug 14, 2026
Remaining:247 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
New 8,500sq ft maintenance facility with entrance, main drive, and parking.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
October 6, 2025
Review Complete
October 6, 2025
Construction Start
November 18, 2025
Expected Completion
August 14, 2026
๐Related Projects
Property Owner
๐ค
Central ISD
Contact: Justin Risner, Superintendent of Central ISD
7622 US Highway 69, Pollock, Texas 75969
Design Firm
๐๏ธ
McKinley Golden Associates
5 projects ยท $8.2M
415 South First Street Suite 300A, Lufkin, Texas 75901