๐Review Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
LTISD Educational Facilities Campus - Phase 1 - Private Drive & Reimers-Peacock Public Roadway
Near 21103 State Hwy 71, TX, 78669
๐Project Overview
$53K
Est. Cost
6,500
Square Feet
1y 2mo
Duration
258
Days Left
๐Scope of Work
6,500 SF of sidewalk and curb ramps
๐ Project Timeline
Registered
October 8, 2025
Review Complete
October 8, 2025
Construction Start
June 15, 2025
Expected Completion
August 15, 2026
๐บ๏ธLocation
๐Related Projects
๐คMore by Lake Travis ISD
Property Owner
๐ค
Lake Travis ISD
Contact: Robert Winovitch
2 total projects
16101 W. State Hwy. 71, Bldg. B, Austin, Texas 78738
(512) 533-5963
Design Firm
Registered Specialist
๐
KATHY ANN,RILEY
RAS #254
1408 NORTHRIDGE DR, AUSTIN, TX 78723
(512) 762-6349