📝Review Complete🔧 Alteration/Renovation💵 This project is privately funded, on private land for private use.
Topline Nails Bar
8481 West State Hwy 29 Suite 300, Leander, TX, 78641
📊Project Overview
$250K
Est. Cost
3,250
Square Feet
6 months
Duration
141
Days Left
📋Scope of Work
3250 SqFt
📅Project Timeline
Registered
October 17, 2025
Review Complete
October 17, 2025
Construction Start
October 20, 2025
Expected Completion
April 20, 2026
🗺️Location
Property Owner
Design Firm
Registered Specialist
📋
MARTELLE,LUEDECKE
RAS #1770
2319 CR 114, BURNET, TX 78611
(512) 459-2121