๐Review Complete๐ง Renovation/Alteration๐ต This project is privately funded, on private land for private use.
Jim Bass Office/Showroom Remodel
4032 Houston Harte Fwy, San Angelo, TX, 76904
Construction50%
๐Project Metrics
TDLR #TABS2026003686$1.2M
Project Value
51,515
Square Feet
$23/sqft
Cost/SqFt
6 months
Duration
Registered:Oct 19, 2025
Start:Nov 17, 2025
Target:May 20, 2026
Remaining:161 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Office/Showroom Reemodel
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
October 19, 2025
Review Complete
October 19, 2025
Construction Start
November 17, 2025
Expected Completion
May 20, 2026
๐Related Projects
Property Owner
Design Firm
๐๏ธ
L Henry Trask - Architect
4 projects ยท $12.1M
14 South Jefferson, San Angelo, Texas 76901