📝Review Complete🏗️ New Construction💵 This project is privately funded, on private land for private use.
Salty Pelican
403 E Hwy 332, Surfside Beach, TX, 77541
Construction50%
📊Project Metrics
TDLR #TABS2026004543$4.0M
Project Value
9,400
Square Feet
$426/sqft
Cost/SqFt
8 months
Duration
Registered:Oct 29, 2025
Start:May 7, 2025
Target:Jan 1, 2026
Remaining:22 days
📝
Review Complete
Design review complete, construction may proceed
📋Scope of Work
Brand New Bar and Restaurant
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
October 29, 2025
Review Complete
October 29, 2025
Construction Start
May 7, 2025
Expected Completion
January 1, 2026