๐Review Complete๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
Charles Schwab
3000 Schwab Way, Westlake, TX, 76262
Construction50%
๐Project Metrics
TDLR #TABS2026005414$775K
Project Value
79,675
Square Feet
$10/sqft
Cost/SqFt
4 months
Duration
Registered:Nov 7, 2025
Start:Aug 4, 2025
Target:Nov 28, 2025
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Temporary parking lot installation.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
November 7, 2025
Review Complete
November 7, 2025
Construction Start
August 4, 2025
Expected Completion
November 28, 2025