๐Ÿ“‹Project Registered๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

BU04B: Buffalo Bayou Downtown Trail - East (Greenway Improvement) - Austin St to Runnels St On-Stre

Commerce Street between Austin St and Elysian St; Elysian Street between Commerce St and Runnels St, Houston, TX, 77002
Pre-Construction15%

๐Ÿ“ŠProject Metrics

TDLR #TABS2026005696
$770K
Project Value
1
Square Feet
$770000/sqft
Cost/SqFt
6 months
Duration
Registered:Nov 12, 2025
Start:Mar 17, 2026
Target:Sep 17, 2026
Remaining:281 days
๐Ÿ“‹

Project Registered

Project has been registered with TDLR and is in pre-construction phase

๐Ÿ“‹Scope of Work

Implementation of a Shared-Use Path within COH and TXDOT ROW to connect Austin St to Runnels St; approx. 0.3 miles

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
November 12, 2025
Construction Start
March 17, 2026
Expected Completion
September 17, 2026

๐Ÿ—บ๏ธProject Location

Loading map...

Quick Actions

TDLR ID: TABS2026005696

Design Firm

Registered Accessibility Specialist

๐Ÿ“‹
LAURA,FULKERSON
RAS #96
PO BOX 2008, MASON, TX 76856