๐Review Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Intersection Safety Improvements
Various Locations, Tyler, TX, 75702
Construction50%
๐Project Metrics
TDLR #TABS2026005743$601K
Project Value
1,000
Square Feet
$601/sqft
Cost/SqFt
9 months
Duration
Registered:Nov 12, 2025
Start:Mar 1, 2026
Target:Dec 1, 2026
Remaining:356 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Intersection Improvements at Grande Blvd, Sutherland Dr, Rose Rudman Trail crossing of New Copeland Rd
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
November 12, 2025
Review Complete
November 12, 2025
Construction Start
March 1, 2026
Expected Completion
December 1, 2026