📝Review Complete🔧 Renovation/Alteration💵 This project is privately funded, on private land for private use.
Hailiang Copper Tubing Facility Building # 16 Renovation Project Phase 2 - Production Line 2 and 3
5000 NW Frontage Road, Sealy, TX, 77474
Construction50%
📊Project Metrics
TDLR #TABS2026005934$4.9M
Project Value
174,000
Square Feet
$28/sqft
Cost/SqFt
6 months
Duration
Registered:Nov 14, 2025
Start:Feb 16, 2026
Target:Jul 31, 2026
Remaining:233 days
📝
Review Complete
Design review complete, construction may proceed
📋Scope of Work
TO ADD EQUIPMENT FOUNDATIONS, PITS, CRANES, EQUIPMENT PLATFORM, AND ASSOCIATED EQUIPMENTS MECH., ELEC., PLUMBING WORKS AND DEVICES OF THE PHASE 2 PRODUCTION LINE 2 & 3 ( 173,666.7 S.F.)
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
November 14, 2025
Review Complete
November 14, 2025
Construction Start
February 16, 2026
Expected Completion
July 31, 2026
Property Owner
Design Firm
🏛️
Kide International (The States) LLC
1001 S Dairy Ashford Rd Ste 380, Houston, Texas 77077