๐Ÿ“‹Project Registered๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

TX9-621 Leander

SWC Hwy 29 and Ronald Reagan, Leander, TX, 99037

๐Ÿ“ŠProject Overview

$4.5M
Est. Cost
3,611
Square Feet
10 months
Duration
512
Days Left

๐Ÿ“‹Scope of Work

Ground Up Bank of America new construction

๐Ÿ“…Project Timeline

Registered
November 18, 2025
Construction Start
June 26, 2026
Expected Completion
April 26, 2027

๐Ÿ—บ๏ธLocation

Property Owner

๐Ÿ‘ค
Bank of America
Contact: JLL
100 N Tryon St, Charlotte, North Carolina 28255
(214) 789-5347

Design Firm

๐Ÿ›๏ธ
Interior Architects
6 total projects
PO Box 45179, San Francisco, California 99037
(206) 773-2718

Registered Specialist

๐Ÿ“‹
DAVID C,DEMING
RAS #129
16222 CRYSTAL HILLS DR, AUSTIN, TX 78737
(512) 940-4226

Tenant

๐Ÿข
Bank of America
214.709.9783

Official Record

View on TDLR
ID: TABS2026006223