City of Palmview Fire Station and EOC Bldg
1803 Marla St, Palmview, TX, 78572
Pre-Construction15%
๐Project Metrics
TDLR #TABS2026006527$5.0M
Project Value
15,300
Square Feet
$327/sqft
Cost/SqFt
1y 2mo
Duration
Registered:Nov 21, 2025
Start:Feb 2, 2026
Target:Apr 1, 2027
Remaining:477 days
๐
Project Registered
Project has been registered with TDLR and is in pre-construction phase
๐Scope of Work
New Fire Station and EOC Bldg
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
November 21, 2025
Construction Start
February 2, 2026
Expected Completion
April 1, 2027